Published November 14 2026.
Scotia Place, the arena the City of Calgary is building next to the Saddledome in Victoria Park, reached its “topping off” milestone in September 2026, when the last piece of structural steel went into the main arena. The City’s October 21 2026 newsletter, its latest, also reports the main arena roof deck complete, all roof trusses installed on the Esso Community Arena and glass going in at the southwest entrance. The City still lists the opening as fall 2027: it plans to hand the keys to the tenant, Calgary Sports and Entertainment Corporation (CSEC), in fall 2027 and to open to the public for the 2027/2028 NHL season. No opening day has been announced.
Scotia Place construction at a glance
| Item | Status as the City of Calgary states it |
|---|---|
| Latest City update | October 2026 newsletter, dated October 21 2026, covering September |
| Main arena steel | Complete; final piece installed in September 2026 (“topping off”) |
| Steel installed in the main arena | About 7,760 metric tonnes |
| Main arena roof deck | Installation complete |
| Esso Community Arena | All roof trusses installed; roofing nearly 50% complete |
| Workers on site | Over 800 a day |
| Height | 32 m (105 feet), street level to top of roof |
| Opening | Fall 2027; open to the public for the 2027/2028 NHL season |
| Opening day or first event | Not announced |
Checked November 13 2026 on the City of Calgary’s Scotia Place construction page, project updates list, newsletters for May to October 2026, Scotia Place home page and frequently asked questions.
What the September 2026 update reports
The City’s October 2026 newsletter lists these September highlights:
- The main arena reached its “topping off” milestone with the installation of the final structural steel piece.
- Main arena roof deck installation is complete.
- Steel installation began for the reassembly of the historic Stephenson Building.
- Glass installation progressed at the southwest entrance.
- The first “cauldron fins” were installed.
- Construction advanced on the indoor public plaza and the restaurant spaces on the north side.
- All Esso Community Arena roof trusses were installed, with roofing nearly 50% complete.
The September 18 2026 newsletter describes the topping off ceremony as “a long-standing construction tradition that recognizes the completion of a building’s structural steel frame”. It puts the steel installed in the main arena at about 7,760 metric tonnes (over 17 million pounds). The same newsletter’s August highlights say the east side of the roof was enclosed, crews were closing in the centre of the main arena, and precast seating installation had passed the halfway point in the main bowl.
Scotia Place construction timeline
This timeline combines the City’s construction page with its monthly newsletters. Each month is the month the work happened, not the date the newsletter was sent.
| When | Milestone |
|---|---|
| July 22 2024 | Ground-breaking and design reveal; excavation begins |
| January 2025 | Foundation construction starts |
| October 2025 | Steel rises above ground level |
| January 2026 | Precast concrete for the seating bowl begins |
| March 2026 | First roof truss installed |
| April 2026 | Trusses span the full 104 m width of the bowl; first cauldron panels on the south side |
| May 2026 | Roof deck about one-third complete |
| July 2026 | Precast in the upper main bowl complete; first concrete slab on the event level |
| September 2026 | Topping off: final structural steel in the main arena; roof deck complete |
| Fall 2027 | Keys to CSEC; open for the 2027/2028 NHL season (target) |
Sources: City of Calgary Scotia Place construction page and the Scotia Place construction updates page (2024 and 2025 rows), the July 2026 newsletter’s year in review (October 2025 to March 2026), and the May, June, August, September and October 2026 newsletters. By this site’s calculation, the City’s fall 2027 target falls a little over three years after the July 2024 ground-breaking.
The building by the numbers
The City’s construction page says each steel roof truss weighs roughly 79 metric tonnes and measures 56 m long by 12 m high. The July 2026 newsletter says the finished roof will carry up to 181 metric tonnes (400,000 lbs) of lighting, sound and event equipment, against the Saddledome’s rigging capacity of about 40.8 metric tonnes (90,000 lbs). By this site’s calculation from those two figures, that is about 4.4 times the Saddledome’s load.
The same newsletter says the underground loading dock will have six loading bays and three internal broadcast truck bays, and that 14 Avenue SE is being raised by 2 m (6.5 feet) to give street-level access. The October newsletter says the roof will carry more than 600 solar panels over 1,500 square metres, “roughly the size of an NHL ice surface”, producing enough electricity for about 30 homes a year. It also says the building will connect to Calgary’s District Energy System for heat.
What will be inside
The City’s Scotia Place home page lists the parts of the building that are now taking shape:
| Space | What the City says |
|---|---|
| Main arena | One of two NHL-sized ice surfaces in the building |
| Esso Community Arena | 1,000 seats; bookable ice with community rates 15% below the average City of Calgary rental rate |
| Parkade | 450 stalls |
| Dining | Five dining destinations, including restaurants, a food market and a café, along the north and west blocks |
| Indoor community plaza | Open to the public outside event times |
| Outdoor plazas | North, south and west; the south plaza gets a large viewing screen and becomes the future home of the Flames’ Red Lot |
| Northwest entrance | Main entrance, with food and drink, the Calgary Flames flagship store and access to the main arena |
Seating capacity, cost and ownership are covered in our Scotia Place guide.
The Stephenson Building is being rebuilt
One older building is part of the new one. The City’s frequently asked questions say the Stephenson & Co. Grocers Building was “carefully deconstructed and cataloged brick by brick” during site preparation and stored off site for future use within Scotia Place. The September and October 2026 newsletters both report that steel installation has begun for its reassembly. The City’s pages read for this update do not say where in the complex it will stand or what it will be used for.
Roads and the 6 Street SE underpass
The City is building a second road crossing under the CPKC rail line at the same time. According to the City’s 6 Street SE underpass page, construction runs in phases until an expected opening in 2028. From October 22 2026 until October 2027, traffic on 9 Avenue SE uses the rebuilt north lanes in both directions. The October newsletter says the change reopens 6 Street SE north of 9 Avenue SE, restores the west driveway into The Confluence and opens a new multi-use pathway along the north side of 9 Avenue SE.
The City’s newsletters tell visitors to expect periodic lane restrictions and road closures across the Culture + Entertainment District while work continues, and point to the C+E Access Map for current closures. For events at the Saddledome or the BMO Centre during construction, see getting to Victoria Park, Stampede Park parking and the Victoria Park/Stampede CTrain station guide.
What has not been announced
- An opening day or first event. The City gives fall 2027 and the 2027/2028 NHL season only.
- A demolition date for the Saddledome. The City’s questions page says it will demolish the Saddledome when Scotia Place opens; see what happens to the Saddledome after Scotia Place opens.
- What the rebuilt Stephenson Building will hold.
- Parkade rates.
The City has published a newsletter about once a month since May 2026, and the last one is dated October 21 2026. This page will be updated when the next one appears. The wider district plan, including the hotel on Stampede Park and the Green Line, is on our Victoria Park development page, and this season’s last events at the old arena are in Saddledome concerts and on our Calgary Flames page. The old arena’s story is in the Saddledome history, and this week’s events in the district are in What’s On at Victoria Park.
Frequently asked questions
When does Scotia Place open?
The City of Calgary lists fall 2027. Its questions page says keys go to CSEC in fall 2027 and the building opens to the public for the 2027/2028 NHL season. No date has been announced.
Is Scotia Place on schedule?
The City’s construction page still says Scotia Place is “scheduled to open fall 2027”, and the September 2026 newsletter refers to events “beginning in fall 2027”. The City pages read for this update give no other schedule statement.
What does “topping off” mean?
The City describes it as a construction tradition marking the completion of a building’s structural steel frame. At Scotia Place it was the installation of the final structural steel beam in the main arena, in September 2026.
How tall is Scotia Place?
32 m (105 feet) from street level to the top of the roof, according to the City’s construction page.
Will Scotia Place have parking?
Yes. The City’s Scotia Place home page lists a 450-stall parkade on site. Rates have not been published.
Sources: City of Calgary, October 2026 newsletter (October 21 2026): September progress, solar panels, District Energy, 9 Avenue SE traffic change. Read November 13 2026. City of Calgary, September 2026 newsletter (September 18 2026): topping off, 7,760 tonnes, August progress. Read November 13 2026. August 2026 newsletter (August 18 2026): July progress. July 2026 newsletter (July 22 2026): year in review, rigging capacity, loading dock, 14 Avenue SE. June 2026 newsletter (June 16 2026): May progress. May 2026 newsletter (May 13 2026): April progress, 104 m trusses. All read November 13 2026. City of Calgary, Scotia Place construction: workers, height, trusses, ground-breaking, foundation, opening target. Read November 13 2026. Scotia Place, Construction Updates: July 22 2024 ground-breaking date. Read November 13 2026. City of Calgary, Scotia Place home page: spaces, parkade, community arena, dining. Read November 13 2026. City of Calgary, Scotia Place frequently asked questions: keys and opening, Stephenson & Co. Grocers Building, Saddledome demolition. Read November 13 2026. City of Calgary, 6 Street SE underpass: 2028 opening, 9 Avenue SE traffic pattern. Read November 13 2026.