Stampede Park hotel: the Autograph Collection hotel, its size and timeline

Published November 21 2026

A Victoria Park/Stampede CTrain platform sign beside the tracks, with the station's red-roofed pedestrian bridge and a brick BMO Centre building behind, in April 2018.
The northbound platform and pedestrian bridge at Victoria Park/Stampede station beside Stampede Park, April 14 2018, before the station rebuild.

Published November 21 2026.

The first hotel on Stampede Park is a 13-storey, roughly 320-room Marriott Autograph Collection hotel by Alberta developer Truman, under construction since a groundbreaking on January 9 2026. It sits at the west entrance to Stampede Park beside the expanded BMO Centre. The Calgary Stampede’s venues site says construction is expected to finish in late 2028; Calgary Municipal Land Corporation (CMLC) says the hotel is expected to open in 2028. Two more Truman and Marriott hotels, a W Calgary and a JW Marriott Calgary, are planned at 15 Avenue and Macleod Trail.

The Stampede Park hotel at a glance

ItemWhat the source saysSource
BrandMarriott’s Autograph Collection; Truman works with Marriott InternationalCalgary Stampede venues site; CMLC
Developer and builderTrumanCMLC groundbreaking release
Height13 storeysCalgary Stampede venues site
RoomsAbout 320Calgary Stampede venues site
SiteAbout 85,000 sq ft at the west entrance to Stampede ParkCalgary Stampede venues site; CMLC
Meeting and ballroom space15,000 sq ftCalgary Stampede venues site
Food and drink space14,000 sq ftCalgary Stampede venues site
Development valueAbout $330 millionCMLC release of June 2 2025
Construction startGroundbreaking January 9 2026Calgary Stampede venues site; CMLC
FinishLate 2028 (Stampede); opening expected in 2028 (CMLC)Both

Checked November 21 2026 on venues.calgarystampede.com, news.calgarystampede.com and calgarymlc.ca.

What will be inside

The Stampede’s hotel development page describes a full-service, upper-upscale lifestyle boutique hotel. Its listed features are:

  • about 320 rooms;
  • 15,000 sq ft of meeting and ballroom space;
  • 14,000 sq ft of food and drink space, with restaurants, a lobby bar, a coffee shop and a rooftop lounge with downtown views;
  • a south-facing terrace with an activity pool, a hot tub and an outdoor bar;
  • an indoor swimming pool and a fitness club.

None of the pages we opened names the restaurants, gives room rates or says when bookings open. In the CMLC groundbreaking release, Truman chief operating officer Tony Trutina says the company will share more about amenities in the coming years.

Where it is

CMLC places the hotel at the west entrance to Stampede Park, steps from the BMO Centre, the rebuilt Victoria Park/Stampede CTrain station and Scotia Place. In the June 2025 release, CMLC president and CEO Kate Thompson says the 17 Avenue SE extension unlocked the site’s potential. The Stampede says the design takes its curved form from Flores LaDue Parade and the expanded BMO Centre, and from the movement of a bucking horse. The June 2 2025 release names NORR Architecture of Chicago and the Calgary firms Scatliff+Miller+Murray and CivicWorks as the design and planning team.

For the station and walking routes around the site, see our Victoria Park/Stampede CTrain station guide and which CTrain station serves which Stampede Park venue. Halls and entrances of the convention centre next door are on our BMO Centre halls guide.

Timeline

DateWhat happenedSource
2019CMLC issues an expression of interest for a hotel; Matthews Southwest Hospitality is chosen as preferred partnerCMLC release, December 6 2022
December 6 2022Matthews Southwest Hospitality announced as partner for a BMO Centre convention hotelCMLC release
June 2 2025Truman announced as development partner; purchase and sale agreement signedCMLC and Calgary Stampede releases
July 2025Site preparation begins, including demolition and utility workCMLC groundbreaking release
January 9 2026Groundbreaking; construction begins, with excavation firstCMLC groundbreaking release; Stampede venues site
2028Opening expected (CMLC); construction finished in late 2028 (Stampede)CMLC hotel page; Stampede venues site

The June 2025 release said construction was expected to begin in late 2025. The January 2026 release says site preparation started in July 2025 and foundation work in early 2026, so the two are consistent on the order of work.

The earlier convention hotel plan

This is not the first hotel announced for Stampede Park. On December 6 2022, CMLC and the Stampede named Matthews Southwest Hospitality as partner for a BMO Centre convention hotel of at least 220 rooms on a 31,000 sq ft parcel at 12 Avenue SE, at the north entrance to Stampede Park and fronting Stampede Trail. That release valued the project at about $80 million and said the hotel could connect directly into the BMO Centre.

The 2025 and 2026 releases describe the Truman hotel as the first hotel on Stampede Park and do not mention Matthews Southwest. None of the CMLC or Stampede pages we opened says what became of the 2022 agreement. CMLC’s hotel development page says the Rivers District Master Plan identifies three hotel sites on Stampede Park.

Two more hotels at 15 Avenue and Macleod Trail

CMLC’s January 9 2026 release says a W Calgary and a JW Marriott Calgary by Truman, at 15 Avenue and Macleod Trail, were then in the regulatory approval process. It says the three hotels together will add more than 700 hotel rooms within a five-minute walk of the BMO Centre. CMLC’s Rivers District Master Plan page adds that two of the three will combine hotel and residential space. No opening dates for the W or the JW Marriott appear on the pages we opened.

Why the partners say a hotel is needed

The partners tie the hotel to convention demand at the BMO Centre, which the June 2025 release calls Western Canada’s largest convention centre since its expansion opened in June 2024. The figures they give cover different periods:

  • 409 events hosted between the June 2024 opening and the June 2 2025 release, with 205 major events booked through 2032 (June 2025 release);
  • upwards of 327 events in 2025 alone, including 47 first-time conferences, with 205 major events booked through 2032 (January 2026 release);
  • a projected contribution of more than a quarter of a billion dollars a year to Canada’s GDP (June 2025 release);
  • the first full-service, convention-oriented hotel built in downtown Calgary in 25 years (June 2025 release).

Those are the partners’ own figures. This site has not found an independent count of BMO Centre events.

What it means for visitors during construction

CMLC’s groundbreaking release says Flores LaDue Parade will need occasional closures during construction, coordinated with district partners and shown on the Culture + Entertainment District access map. The Stampede’s venues site links that map from its Attend An Event menu, under Our Location. Neither page we opened lists closure dates. Until the hotel opens, the nearest existing hotels are on our hotels near the Saddledome and BMO Centre page.

What has not been announced

  • The hotel’s full name, opening date and room rates.
  • Restaurant names and operators.
  • Dates for Flores LaDue Parade closures.
  • Construction start and opening dates for the W Calgary and the JW Marriott Calgary.
  • The outcome of the 2022 Matthews Southwest Hospitality agreement.

Wider plans for the district are on our Victoria Park development page.