Published November 21 2026

Visitors walk past booths of framed paintings and photographs inside a hall during the 2023 Calgary Stampede.
Art displays and visitors at the Calgary Stampede, July 9 2023.

Published November 21 2026.

The Calgary Stampede and Calgary Municipal Land Corporation (CMLC) released the first public look at an updated 20-year master plan for Stampede Park on March 18 2026. The plan divides the park into seven zones, among them a new agriculture building, a live events zone beside Scotia Place, a venue to replace the Big Four Building and an expanded or renovated grandstand and track. The Stampede says funding and phasing for each element will be shared as the plan progresses; as of November 21 2026 its master plan page gives no costs, dates or construction schedule.

Stampede Park master plan at a glance

ItemWhat the source saysSource
First public revealMarch 18 2026Calgary Stampede media release
Length of vision20 yearsCalgary Stampede master plan page
Plan it updatesThe original Calgary Stampede Master Plan of 2004Calgary Stampede master plan page
AuthorsThe Calgary Stampede and CMLC, with Populous and Calgary firm GGACalgary Stampede master plan page
Process18 months of consultationCalgary Stampede master plan page
ZonesSevenCalgary Stampede master plan page
Costs and phasingNot announced; to be shared as the plan progressesCalgary Stampede master plan page

Checked November 21 2026 on corporate.calgarystampede.com, news.calgarystampede.com and calgarymlc.ca.

The seven zones

The Stampede’s master plan page describes each zone as a possible future space or facility. The table restates them in plain terms; the wording of the plan itself is on the Stampede’s page.

ZoneWhat the plan proposesRelated page on this site
Agriculture + AnimalsA new purpose-built agriculture facilityNone yet
Discovery and HeritageStronger First Nations perspective and links with the Elbow River, Stampede Campus and Community Park East, for year-round programming and storytellingElbow River Camp, Sam Centre
Live Events ZoneNext to Scotia Place: commercial development, food and drink, and an outdoor gathering space for year-round eventsScotia Place construction update
Multi-Purpose VenueA new venue intended to replace the Big Four Building, for music and eventsBig Four Building
Stampede GatewayA mixed-use site combining visitor needs such as rideshare access and parking with commercial developmentStampede Park parking and transit
Outdoor Flex SpaceBetter-connected open spaces for the 10-day festival, including the MidwayCalgary Stampede 2027
Stadium and TrackAn expansion or renovation of the original grandstand and trackGMC Stadium

None of the seven entries on the Stampede’s page gives a size, a cost, a site boundary or a date. The plan’s own word for them is “potential”, and the release calls the March announcement a first public reveal.

What the plan replaces and what has been built since 2004

In the March 18 2026 release, Calgary Stampede CEO Joel Cowley says the expanded BMO Centre in 2024 and the projects under way complete the 20-year vision set in 2004, and that the Stampede is now planning the next 20 years. The release and the master plan page list what the new plan responds to:

  • the BMO Centre expansion (see our BMO Centre halls guide);
  • the Nutrien Western Event Centre;
  • Sam Centre and the Stampede Youth Campus;
  • the greening and reclamation of Elbow River Park;
  • the 17th Avenue extension and the Victoria Park/Stampede station rebuild;
  • Stampede Trail;
  • Scotia Place and the Autograph Collection hotel, both still being built.

CMLC’s pages put figures on some of these. It describes the BMO Centre expansion as a $500 million project that opened in June 2024 and a 565,000 sq ft building. It says the 17 Avenue SE extension and station rebuild cost $128 million, opened a corridor across 17 Avenue SE into Stampede Park for the first time in 40 years, and shortened the walk across Macleod Trail from 400 m to 60 m. The Stampede’s master plan page says nearly $2 billion in projects are complete or under way in the Culture + Entertainment District.

How it fits the Rivers District Master Plan

The Stampede’s plan sits inside a larger one. CMLC says Calgary City Council approved its Rivers District Master Plan in 2018 as a 20-year vision for redeveloping Stampede Park and east Victoria Park as the Culture + Entertainment District, with four million square feet of mixed-use development and more than 8,000 new residents on 286 acres. CMLC’s Rivers District Master Plan page says the updated Stampede plan, eight years on, translates the district plan’s land use principles into a vision tailored to the Stampede’s own programming needs.

Two acreage figures appear in CMLC material, and they describe different areas. The 286 acres belong to the district master plan for east Victoria Park and Stampede Park. The 504 acres in CMLC’s description of itself cover the whole Rivers District on downtown’s east end, including East Village. CMLC also says it has invested more than $650 million in infrastructure and city-building projects in the district so far.

The Stampede release says the partnership between the Stampede and CMLC dates from 2016 and that the new plan was written together so it lines up with the district plan. CMLC president and CEO Kate Thompson is quoted in the release describing the goal as balancing the Stampede’s specific needs with the district plan’s wider goals.

Stampede Trail: first phase built, second phase not scheduled

Stampede Trail, the street formerly called Olympic Way, is one district project already on the ground. CMLC describes it as a four-block retail and entertainment corridor that can close to traffic for events, with brick pavers, catenary lighting and rolled curbs, funded with $20 million through CMLC’s Community Revitalization Levy.

The sources differ on timing. CMLC’s April 6 2023 groundbreaking release said Phase 1, from 14 Avenue to Agriculture Trail, would be built in 2023, Phase 2, from 12 Avenue to 14 Avenue SE, in 2024, and the project finished in late 2024. CMLC’s current Stampede Trail page says Phase 1 was completed in 2023 and that the timing of Phase 2 will be assessed as Scotia Place and related district work progress. This page uses the current project page for the status.

What this means for visitors now

Nothing in the master plan changes how Stampede Park works today. The plan names no closures and no start dates. The venues it would replace or renovate keep operating: the Big Four Roadhouse runs during the Stampede, as our Big Four Building page records, and the grandstand is home to the rodeo and chuckwagon races described on our GMC Stadium page. The Saddledome’s future is a separate City of Calgary matter covered in what happens to the Saddledome after Scotia Place opens.

What has not been announced

  • Costs or funding for any of the seven zones. The Stampede says funding strategies will be communicated as the plan progresses.
  • Phasing or an order of work, for the same reason.
  • A date for replacing the Big Four Building, or the size of the new venue.
  • The location of the new agriculture facility and whether it replaces an existing building.
  • Whether the grandstand would be expanded or renovated; the plan names both options.
  • A public map of the zone boundaries. The Stampede’s master plan page lists the zones in text, with a graphic titled Thematic Zones, but gives no boundaries or sizes.

Wider district plans, including Scotia Place and street work, are on our Victoria Park development page.